|
Heavy equipment takes a breather from
work on A-LP last week in Ridges Basin./Photo by Patrick
Brawley. |
A mere 2.5 miles from downtown Durango,
earth movers and explosives have been hard at work for the past
several months, and though out of view and earshot, construction
on the Animas-La Plata project has been proceeding roughly according
to plan. In spite of the appearance that a large reservoir and
diversion will become permanent Durango fixtures, a set of lawsuits
have been proceeding through water court with the hope of defeating
a project that is already underway.
The real push for A-LP came in 1868 when an agreement was struck
to compensate Indian tribes with water rights. In 1968, A-LP
was first authorized for construction by the U.S. Congress as
a way of fulfilling that century-old agreement. At that time,
the A-LP project was proposed as a diversion of water from the
Animas and La Plata rivers to principally serve the irrigation
needs of the Southern Ute and Ute Mountain Ute Indian tribes.
The project was never built.
The latest incarnation
In 1988, Congress passed the Colorado Ute Indian Water Rights
Settlement Act, which specifically quantified the amount of
water owned by the Southern Ute and Ute Mountain tribes. A-LP
then went through more challenges and revisions until a scaled
down version, coined “A-LP Lite,” was authorized
by Congress in 2000. The changed project included a 120,000-acre-foot
(more than 39 billion gallons) reservoir 2.5 miles southwest
of downtown Durango in Ridges Basin. A pumping plant located
near Smelter Rapid and Santa Rita Park would siphon up to 280
cubic feet per second from the Animas River and pump it uphill
to feed the reservoir. Water stored in the reservoir would no
longer be used for agriculture but to serve yet-to-be-determined
municipal and industrial needs in New Mexico and Colorado.
Construction on this project got underway earlier this summer
in the expansive natural bowl of Ridges Basin. Crews have completed
the construction of an inlet sleeve, which will eventually hold
the pipeline to the pumping plant. Presently, work is being
done to excavate the dam outlet works, which will enable water
to be released down Basin Creek and back into the Animas.
|
An expansive view of the area slated
to become A-LP’s reservoir./Photo by Patrick Brawley. |
Blockage in the funding flow
“We’d have a hell of a lot more going on if we
had more money,” said Pat Schumacher, the Bureau of Reclamation’s
projects manager for A-LP.
Last year, $16 million for the project was budgeted through
early October. President Bush’s proposed budget sets aside
an additional $33 million for the 2003 fiscal year which began
at that time. However, the budget has yet to pass, and A-LP
and Schumacher’s crews have been operating on a continuing
resolution, whereby week-to-week funding is awarded based on
last year’s allotment.
Expressing his frustration with the financing stream, Schumacher
commented: “It’d be nice if we could get $250 million
and put it in a bank somewhere and draw money as we need it.
We’d be able to build this project in five years. But
as it stands, we’ve got a seven-year construction schedule
where we’re looking at between $50 and $70 million a year
once we get going.”
Schumacher said the Bureau of Reclamation is looking toward
next year’s excavation of the pump plant site, which will
include blasting and serious earthwork and affect day-to-day
life in Durango more significantly. He also said he has his
eye on the targeted completion date of spring 2008.
Keeping the fight alive
However, a number of people have different plans for Ridges
Basin. While A-LP controversy has been quiet of late, at least
one group is undertaking action to defeat the project.
The Citizens’ Progressive Alliance, a Colorado and New
Mexico watchdog group, is currently pursuing six separate lawsuits
against the Department of Interior and the Animas-La Plata project.
The most significant of the alliance’s legal actions
alleges that the Bureau of Reclamation has failed to do the
necessary upkeep on the A-LP water rights, also known as diligence.
In fact, the group has asserted that the bureau has failed to
do diligence on the water since A-LP’s initial approval
in 1968. Specifically, the alliance’s Philip Doe noted
that the rights were initially agricultural and have not been
changed into municipal and agricultural water rights. In addition,
he said that the point of diversion has changed since 1968 but
not been officially adjusted on the water right. As a result,
Doe said that legally, there is no water for the reservoir that’s
currently being constructed in Ridges Basin.
“The Bureau of Reclamation is going to spend money, and
a bunch of money, even though they don’t have a water
right," he said.
A reservoir with no water?
Doe said that the notion that construction is underway is
distressing, particularly considering there is a current legal
challenge that could end the project.
“You’d think if there was a question about water
rights, they might wait to see what the opinion of the court
is,” Doe said.
“They could literally be building a reservoir that they
have no water for.”
Sunny Maynard, the attorney pressing the group’s lawsuits,
commented: “The Ridges Basin reservoir has no water right
decreed for it. There are really lots of nuts-and- bolts water
issues that it appears opposition groups have never gotten into.”
The alliance was supposed to have a day in court this week.
However, Maynard said
that the Bureau of Reclamation produced a last minute expert
report and delayed the hearing.
“They’ve violated every pre-court disclosure deadline
we’ve had,” she said.
The Bureau’s Schumacher agreed that the nature of the
water right has changed.
"It’s all municipal and industrial now,” he
said. “There’s no irrigation in this project any
more.”
However, he said that the court, and specifically District
Judge Gregory Lyman, will have to determine if the bureau has
done its homework. Schumacher said he’s not concerned
about the trial’s outcome.
“It’s really up to the water court to decide,”
he said. “But I don’t have any fears about a lack
of water rights, particularly because of the track record. The
state has always been supportive of this project.”
History repeating itself
The San Juan Citizens’ Alliance is one opponent of A-LP
that’s currently taking a wait-and-see approach. Chuck
Wanner, the group’s water-issues coordinator, said, “I
don’t think we’re at the point of trying to sue
somebody every time they try to turn a
shovelful of dirt.”
However, he noted that the project’s financial ills
could buy the opposition some time. “The project definitely
isn’t going as they planned,” he said. “Maybe
between now and the time the funding comes through, we’ll
get lucky.”
Michael Black, of Taxpayers for the Animas River, has been
an outspoken opponent of the Animas-La Plata and said that he
concurs with the reasoning behind the lawsuit challenging the
A-LP water right.
“To date, they do not have that water right,”
Black said. “It’s now strictly a municipal
and industrial water right, and they never changed that agricultural
water right.”
Black also said that funding problems may be just the ally
that the local opposition needs.
He noted that while he is not an advocate of war in Iraq,
military action could provide unexpected help.
“I’ve seen this scenario unfold before,”
Black said. “The exact same thing happened
in 1968 when the project was first authorized. The Vietnam War
came along, and A-LP was thrown out. I think history will repeat
itself.”
While Schumacher said he’s not concerned about the diligence
case, funding does cause him some unease. “That’s
what is really hurting us,” he said. “It hasn’t
affected our timeline yet because we’re being pretty creative.
It hasn't affected any
flexibility in our schedule.”
And while the Citizen’s Progressive Alliance awaits
its day in court, crews will be back on schedule, working 9-to-5
through the winter in Ridges Basin and continuing construction
on the reservoir.